Office Fit-Out Cost in Dubai 2026: Price per Sq Ft by Specification Level

Most businesses asking what an office fit-out costs in Dubai are holding a lease, a floor plan, and a board paper that needs a number. The answer depends on two things: the condition in which the landlord hands over the unit, and the specification tier the business genuinely needs. The same 3,000 sq ft floor plate in Business Bay can cost AED 750,000 or AED 2.4 million, and both figures can be entirely reasonable.

Below, we set out indicative 2026 Dubai rates per sq ft by tier, what falls within each tier, the approval sequence that governs the programme, and the points at which cutting costs on an interior fit-out ends up costing more than it saves.

What an Office Fit-Out Costs per Sq Ft in Dubai in 2026

An office fit-out in Dubai costs approximately AED 250 to 1,200+ per sq ft in 2026, depending on the specification tier and handover condition. Most Dubai SMEs taking a Category A unit land between AED 350 and AED 600 per sq ft for a complete Category B fit-out. Premium regional headquarters and client-facing professional services floors in DIFC commonly run AED 700 to AED 1,200+ per sq ft. These are market indications, not quotes, and each figure is subject to a costed proposal after a site survey.

The per-sq-ft metric is where most comparisons break down because contractors include different things in it. A rate quoted for an office fit-out in Dubai usually covers construction, finishes, joinery, and MEP (mechanical, electrical, and plumbing) alterations. It frequently excludes loose furniture, audiovisual equipment, IT hardware, structured data cabling, authority submission fees, and landlord deposits. When two proposals sit AED 150 per sq ft apart, the difference is nearly always in the exclusions rather than the artistry.

The second variable is the unit itself. A tenant inheriting a complete Category A floor with a raised access floor, suspended ceiling, primary HVAC distribution, and fire detection already in place starts from a very different base than a tenant absorbing that infrastructure from shell-and-core. That single difference can double the cost of an identical design.

Office Fit-Out Cost per Sq Ft by Specification Tier

The table below sets out indicative 2026 Dubai rates by specification tier. Rates assume a Category A handover and exclude loose furniture, AV, IT, and authority fees.

Specification Tier Indicative AED per Sq Ft Typically Included Suits
Standard AED 250 to AED 350 Demountable or stud partitions with single-glazed glass fronts, mineral fibre ceiling retained or patched, luxury vinyl tile and carpet tile flooring, recessed LED panels to around 400 lux at desk level, minor FCU relocation and diffuser rework, laminate joinery, standard pantry, surface trunking for power and data Startups, back-office and operations floors, 2 to 3 year leases in JLT, Al Quoz, and secondary Business Bay stock
Mid-Range AED 350 to AED 600 Double-glazed acoustic glass partitioning at 38 to 42 dB, plasterboard bulkheads and open-grid ceiling features, LVT and broadloom carpet, designed lighting with linear and feature pendants, HVAC redesign with added FCUs or VAV boxes and fresh air rebalancing, veneered or spray-finish joinery, full pantry with solid surface worktops, structured Cat 6A cabling, basic meeting room AV Professional services firms, regional sales offices, 5-year leases in Business Bay, Sheikh Zayed Road, and DMCC towers
Premium AED 600 to AED 900 Frameless double-glazed partitions with deflected head detail, full plasterboard and timber ceiling design, engineered timber and large-format stone to reception, decorative lighting on dimming control, substantial MEP rework including supplementary cooling to server and boardroom, bespoke veneer and stone joinery, raised access floor adjustments, integrated room booking and video conferencing Regional headquarters, law and advisory firms, family offices, client-facing floors in DIFC and Gate Village
Flagship AED 900 to AED 1,200+ Structural alterations and feature staircases, full MEP replacement, Cosentino Dekton and Arabescato marble surfaces, de Gournay or Phillip Jeffries wall coverings, acoustic consultant input on boardrooms, KNX or Crestron lighting and blind control, fully integrated AV, custom furniture programme Multinational HQs, investment firms, buildings where the office is part of the brand proposition

What moves a project up a tier is rarely the aesthetic. It is the partition system, the ceiling strategy, and the extent of MEP intervention. Swapping single-glazed partitions for double-glazed acoustic units with a deflected head detail adds cost per linear metre, and it is the difference between a boardroom that holds a confidential conversation and one that does not. Taking down an existing ceiling grid to expose services means new sprinkler drops, acoustic treatment, and painted soffits, which usually costs more than keeping the grid.

Budget furniture, AV, and IT as separate lines. Loose furniture for a Dubai office typically runs AED 4,000 to AED 15,000 per workstation position once task seating, desking, storage, and meeting furniture are counted, and a specified European furniture programme sits well above that. All ranges on this page are indicative 2026 Dubai market figures and are subject to a costed proposal.

Worked Example: Budgeting a 3,000 Sq Ft Dubai Office at Each Tier

A 3,000 sq ft Category A office accommodating roughly 30 to 35 people produces the following indicative totals.

Tier Rate per Sq Ft Indicative Fit-Out Total Plus Furniture, AV, and IT
Standard AED 250 to AED 350 AED 750,000 to AED 1,050,000 AED 150,000 to AED 300,000
Mid-Range AED 350 to AED 600 AED 1,050,000 to AED 1,800,000 AED 300,000 to AED 550,000
Premium AED 600 to AED 900 AED 1,800,000 to AED 2,700,000 AED 550,000 to AED 900,000

On a mid-range scheme at AED 1.4 million, the split is usually close to: construction, partitions, ceilings, and finishes 40% to 45%; MEP alterations 18% to 25%; joinery 12% to 18%; loose furniture 10% to 15%; AV and structured cabling 5% to 8%; design fees, approvals, and submission costs 3% to 5%.

Add contingency on top of that, not inside it. For a surveyed Category A unit with as-built MEP drawings available, 5% is defensible. For an unsurveyed unit, a shell-and-core floor, or a building where the as-builts do not match reality, 10% to 15% is realistic. Nearly every overrun we see on Dubai offices traces back to services discovered above a ceiling that nobody had opened before works started. Our corporate office fit-out project shows how these proportions resolve in a delivered scheme rather than a spreadsheet.

Quick tip: Ask every contractor for the cost per sq ft and the total contract sum separately, alongside the exclusions list. Rates are often presented in a form that makes the number look better, and applying an attractive rate to an inflated area calculation can appear cheaper than it is. Confirm whether the area quoted is net internal or gross leasable.

Cat A and Cat B Fit-Outs Explained, and What a Dubai Landlord Hands Over

A Category A fit-out is the landlord’s base build: a floor finished to a usable but unbranded standard, typically with a raised access floor or screed, suspended ceiling grid, primary HVAC distribution, basic lighting, fire detection and sprinklers, and finished core washrooms and lift lobbies. It is a lettable empty floor, not a working office.

A Category B fit-out is everything the tenant adds to make the space operational and specific to their business: partitions, meeting rooms, reception, joinery, pantry, feature ceilings and lighting, branded finishes, power and data to workstations, AV, and furniture.

Shell and core means the landlord has delivered only the structure, facade, core, and risers. There is no ceiling, no floor finish, no lighting, and often no HVAC beyond a capped connection at the riser. The tenant absorbs the entire MEP infrastructure cost, which is why shell-and-core commercial fit-out projects carry a materially higher cost per sq ft than a Category B scheme on a completed Category A floor, commonly AED 80 to AED 180 per sq ft more for comparable specifications.

Handover Condition Landlord Typically Provides Tenant Typically Absorbs
Shell and core Structure, facade, core washrooms, lift lobby, capped services at riser All HVAC and electrical distribution, small power, fire detection and sprinklers, ceilings, floors, lighting, plus the full Category B scope
Category A Raised floor or screed, ceiling grid, primary HVAC, base lighting, fire detection, sprinklers, DB and risers Partitions, joinery, pantry, finishes, lighting design, workstation power and data, AV, furniture
Category B in place (assignment or sublease) A previous tenant’s completed office Strip-out of unwanted elements, reconfiguration, refresh of finishes, and reinstatement liability at lease end

Three commercial points are usually negotiable and routinely left on the table. First, landlord contribution: a cash contribution towards Category B works, often expressed per sq ft. Second, the rent-free period, which is the tenant’s real fit-out funding mechanism and should be long enough to cover approvals as well as construction. Third, dilapidations. Many Dubai leases require reinstatement to Category A condition at expiry, and that liability should be priced at the outset rather than discovered in year five. A scheme built with demountable partitions and a retained ceiling grid costs far less to reinstate than one built in blockwork.

The Cost Drivers That Move a Dubai Office Between Specification Tiers

Seven variables account for most of the spread between an AED 300- and an AED 700-per-sq-ft scheme.

  • MEP and HVAC rework. Relocating or adding fan coil units, introducing VAV boxes, and rebalancing fresh air provision is the single largest swing factor. Extending existing distribution is cheaper than redesigning a zone. Still, a dense open-plan layout dropped onto cellular HVAC zoning will not perform, and diffuser adjustment does not fix it afterwards.
  • Slab-to-slab height. Older Business Bay and Sheikh Zayed Road floor plates often have limited void depth. Where height allows, removing the ceiling for an exposed services look requires new sprinkler drop-down heads, acoustic rafts or sprayed treatment, and tidy containment.
  • Glass partitioning. Single-glazed frameless systems are the entry point. Double-glazed acoustic units at 38 to 45 dB, slim framing, integrated blinds, and compliant manifestation can double the linear metre rate.
  • Floor power and data strategy. A raised access floor with floor boxes is flexible but costs more than dado trunking and perimeter containment. Where a raised floor already exists in Category A, use it rather than remove it.
  • Meeting room and boardroom acoustics. Partitions taken to the slab with a deflected head detail, mineral wool infill, acoustic door sets with drop seals, and sealed service penetrations cost considerably more than partitions stopped at ceiling level.
  • Pantry and washroom works. Keeping wet areas on existing drainage runs is the cheapest route. Moving a pantry away from the riser means new waste runs, falls within a limited floor void, and often a pumped solution.
  • Furniture specification. The most elastic line in any budget. The same workstation footprint can cost AED 3,500 or AED 18,000 per position, depending on the manufacturer and warranty.

Approvals and Authority Fees in the Dubai Office Fit-Out Budget

Approvals are on the critical path for every site activity. No chargeable site work begins until permits are in place. The sequence runs: measured survey and design sign-off, coordinated architectural and MEP drawings, landlord or building management No Objection Certificate (NOC), authority submission, permit issue, then site mobilisation.

Which authority receives the submission depends on where the unit sits:

  • Dubai Municipality (DM) issues building permits for fit-out works involving structural, external, and MEP alterations in mainland buildings. A conventional office fit-out for clients planning interior design in Business Bay follows this route, subject to the building management NOC.
  • Dubai Civil Defence (DCD) reviews fire and life safety: sprinkler head relocation, smoke-detection coverage, escape-route widths and travel distances, emergency lighting, and fire-rated compartmentation. Any change to the partition layout triggers a DCD review.
  • The DIFC Authority operates its own fit-out approval route for tenants inside the district, separate from the DM submission, with its own drawing standards and contractor registration requirements. Anyone planning interior design in DIFC should allow time for that route specifically rather than assuming the mainland process.
  • DMCC runs a comparable fit-out NOC and approval process for tenants at JLT and Uptown Tower.
  • DEWA handles load applications and final sign-off where additional electrical capacity is required, which is common when occupancy density increases or supplementary cooling is added.

Authority fees are modest relative to the construction cost, but the drawing preparation, coordination, and resubmission effort are not, and they should appear as a line item in any proposal. We prepare approval packages in-house and typically secure them within 2 to 4 weeks. That is our typical experience across Dubai office projects, not a guarantee. Buildings with slow management offices or incomplete as-built records take longer to process.

Realistic Fit-Out Programme Durations From Design Sign-Off to Handover

Indicative durations from design sign-off to furnished handover, assuming a Category A unit and no structural alteration:

Office Size Approvals Procurement Site Works Total From Design Sign-Off
Up to 3,000 sq ft 2 to 4 weeks Runs in parallel 6 to 8 weeks 9 to 13 weeks
3,000 to 10,000 sq ft 3 to 5 weeks 4 to 8 weeks, overlapping 10 to 14 weeks 14 to 20 weeks
10,000 sq ft and above 4 to 8 weeks 8 to 14 weeks, overlapping 16 to 24 weeks 22 to 32 weeks

Long-lead items dictate the programme more than labour does. Double-glazed partition systems, bespoke veneer joinery, specified European furniture, electrical switchgear, and certain lighting ranges carry lead times of 8 to 16 weeks. Compressing a programme is possible and expensive: overtime and night work permits, multiple trades in the same area, local substitution of specified items, and air freight instead of sea freight can save 2 to 4 weeks on a mid-sized office, typically adding 8% to 15% to the contract sum. The deadline driving all of this is usually the expiry of the rent-free period, so work backwards from that date when setting the design sign-off deadline.

Refitting an Occupied or Dated Office Versus Fitting Out a New Unit

Refitting an existing office is not automatically cheaper than fitting out a new unit. Strip-out, waste segregation, and disposal at approved facilities carry their own costs; demolition still requires permission, and working around a live business imposes constraints that an empty floor does not. An office renovation delivered in phases, or restricted to evenings and weekends so trading continues, typically carries a 15% to 30% premium over the same scope in an empty unit, driven by protection works, repeated set-up and clear-down, and reduced trade productivity.

Worth retaining in most refits: the suspended ceiling grid where tiles can be replaced, primary HVAC distribution if the layout broadly holds, raised access floor panels, sound partition studwork, and joinery carcasses that can take new fronts and worktops.

Rarely worth keeping: lighting from earlier generations that fails to meet current efficiency and lux expectations; data cabling installed before Cat 6A; glazing gaskets and seals on partitions that are over roughly 8 years old; and pantry appliances and worktops, which show wear faster than anything else on an occupied floor.

Where Dubai Businesses Overspend, and Where Cutting Cost Backfires

The most common overspend is space, not specification. Enclosed offices and meeting rooms get provided against an aspirational headcount rather than measured occupancy, and businesses pay construction costs for rooms that sit empty 80% of the week. A short occupancy study, conducted before the layout is frozen, regularly removes two meeting rooms from a brief. Close behind: large-format stone in circulation areas that people don’t stop to look at, and AV specified to a capability the team doesn’t use.

The false economies cost more over a lease term than the savings they generate:

  • Thin, non-acoustic partitions stopped at ceiling level. The complaints start in week two, and the remedial work means taking the ceiling down again.
  • Under-specified HVAC. Dubai summer load, combined with dense occupancy, exposes cooling shortfalls immediately, and retrofitting supplementary cooling into a finished office requires new pipework through completed ceilings, builder’s work, and a second DEWA load application.
  • Cheap ironmongery and door closers on high-traffic doors, which fail within 12 to 18 months.
  • Undersized electrical distribution that leaves no spare capacity, making any future expansion a new application rather than a new circuit.

Budget drift between the tender and the final account almost always arises from provisional sums and prime cost allowances. A proposal carrying a provisional sum for MEP alterations and a PC rate for joinery is not a fixed price. Read the specification and the exclusions before the headline rate, because the cheaper proposal is often the one with fewer items.

Design and Build Under One Contract Versus Separate Designer and Contractor

Design and build means one party carries design, approvals, and construction under a single contract. The traditional route means appointing a designer, developing the scheme, then tendering it to contractors who price the completed drawings.

Factor Design and Build, Single Contract Separate Designer and Contractor
Cost certainty Set earlier, with buildability priced during design Set after tender, which can be 8 to 12 weeks later
Responsibility One contract, one accountable party Split, with design intent and build quality argued between parties
Variation risk Lower, as MEP coordination happens before pricing Higher, as drawing gaps become contractor variations
Speed to site Faster, with approvals prepared alongside detailing Slower, with a distinct tender period
Best suited to Most commercial offices up to 20,000 sq ft, lease-driven programmes Large or highly bespoke projects where competitive tendering on a fully specified design is worth the time

The two-stage route has a genuine place. On a 30,000 sq ft headquarters with a named architect and an acoustic consultant, tendering a fully resolved design to several contractors is sound procurement. On a 4,000 sq ft office with a rent-free clock running, the coordination gap between designer and contractor is where the budget leaks.

We work under a single contract. Concept design, photorealistic 3D interior design, working drawings and joinery details, MEP coordination, authority approvals, construction, furniture procurement, and handover are all handled by us, with 1 project manager as your point of contact throughout. Our office interior design work and broader turnkey interior solutions are delivered by the same senior designer who develops the concept and then supervises it on site. We have completed over 340 projects since 2022, and 3D designs are included free with any project.

Office Fit-Out Cost in Dubai: FAQs

Is a per sq ft rate quoted on net or gross area?

Confirm this in writing. Fit-out rates should be applied to net internal area, the usable floor you are actually building within. Lease documents often state gross leasable area, which includes a share of common parts and can be 10% to 20% larger. Applying a rate to the gross figure inflates the total without changing the scope.

Can the fit-out be funded from the rent-free period?

Partly, in most cases. A rent-free period offsets occupancy costs during construction rather than paying the contractor, so it funds the fit-out indirectly by removing double rent. Larger tenants also negotiate a separate landlord contribution per sq ft towards Category B works. Both should be agreed at heads of terms, before the lease is signed.

What happens to the fit-out at the end of the lease?

Many Dubai leases contain a reinstatement clause requiring the floor to be returned to Category A condition, with partitions removed and ceilings and finishes made good. Price that liability at the design stage. Demountable partitions and a retained ceiling grid substantially reduce reinstatement costs compared with blockwork and bonded finishes.

Do fit-out costs differ between DIFC, Business Bay, and JLT?

Yes, though the construction scope drives more of the difference than location does. Variance comes from building management requirements, restricted working hours in occupied towers, service lift booking, approved contractor lists in some free zone buildings, and the specification-level expectations tenants in each district have. DIFC schemes typically sit a tier higher for that reason.

Should a contingency be included in the contract sum?

Hold it separately, under your control, rather than inside the contractor’s figure. We advise 5% for a surveyed Category A unit with reliable as-built drawings, and 10% to 15% for a shell-and-core floor or any unit where the ceiling void has not been opened and inspected before pricing.

Request a Costed Office Fit-Out Proposal From Kat Black Design Studio

Get your office fit-out priced on your actual unit, not a market average. Send us the floor plan, the handover condition, and your headcount, and we will return a costed proposal with design and fit-out under one contract, 1 project manager as your point of contact, in-house approvals, and 3D designs included free of charge.

Reach us on WhatsApp at +971 58 228 2450, email info@katblackuae.com, or use our contact page. If you arrived here budgeting for a home rather than an office, our guide to how much interior design costs in Dubai covers residential rates in the same detail.

Khalil
Khalil
We provide suitable and timely solutions to meet our clients expectations and needs this is essential for a trusting relationship with our clients and partners.
Frequently Asked Questions

Request a Free Consultation

Kat Black Design Studio has completed projects across Dubai Hills Estate, Palm Jumeirah, Emirates Hills, DIFC and beyond. If you are ready to discuss your interior design, renovation, fit-out or landscaping project anywhere in Dubai or the UAE, request a complimentary consultation today, with no obligation.

Or contact us directly via WhatsApp. All enquiries receive a response within two business hours.








    This website stores cookies on your computer. Cookie Policy